§ 10.04.07. Wastewater discharge permits.  


Latest version.
  • A.

    Mandatory permits. All industries proposing to connect or to commence a new discharge to the wastewater disposal system shall obtain a wastewater discharge permit before connecting to or discharging into the wastewater disposal system if the discharge would result in the industry being classified as a significant industrial user. All existing significant industrial users or industrial users subject to national categorical pretreatment standards under Section 307(b) and (c) of the Act connected to or discharging into the wastewater disposal system shall obtain a wastewater discharge permit within one hundred eighty (180) days after the effective date of the ordinance from which this section is derived.

    B.

    Permit application. Users required to obtain a wastewater discharge permit shall complete and file with the superintendent, an application in the form prescribed by the superintendent and accompanied by a fee of forty dollars ($40.00). Existing users shall apply for a wastewater discharge permit within thirty (30) days after the effective date of the ordinance from which this section is derived, and proposed new users shall apply at least sixty (60) days prior to connecting or discharging to the wastewater disposal system. In support of the application, the user shall submit, in units and terms appropriate for evaluation, the following information:

    1.

    Name, address, and location (if different from the address );

    2.

    SIC number according to tire Standard Industrial Classification Manual, Bureau of the Budget, 1972, as amended;

    3.

    Wastewater constituents and characteristics including but not limited to those governed by sections 10.04.02 and 10.04.03 as determined by a reliable analytical laboratory; sampling and analysis shall be performed in accordance with procedures established by the EPA pursuant to Section 304(g) of the Act and contained in 40 CFR, Part 136, as amended;

    4.

    Time and duration of discharge;

    5.

    Average daily and thirty (30) minute peak wastewater flow rates, including daily, monthly and seasonal variations, if any;

    6.

    Site plans, floor plans, mechanical and plumbing plans and details to show all sewers, sewer connections, and appurtenances by the size, location and elevation;

    7.

    Description of activities, facilities and plant processes on the premises including all materials which are or could be discharges, including sludges, floats, skimmings, etc.;

    8.

    Where known, the nature and concentration of any pollutants in the discharge which are limited by any city, state or national categorical pretreatment standards, and (for an existing discharge) a statement regarding whether or not the pretreatment standards are being met on a consistent basis and, if not, whether additional operation and maintenance and/or additional pretreatment is required for the user to meet applicable pretreatment standards. If additional operation and maintenance and/or pretreatment will be required, a proposed schedule by which the changes will be completed shall be submitted. The completion date in this schedule shall not be later than the compliance date established for the applicable pretreatment standard. The schedule shall contain increments of progress in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the user to meet the applicable pretreatment standard. No increment shall exceed nine months in length, and progress reports concerning each increment shall be submitted within fourteen (14) days following each increment date;

    9.

    Each product produced by type, amount, and rate of production;

    10.

    Type and amount of raw materials processed (average and maximum per day);

    11.

    Number of full and part time employees, and hours of work; and,

    12.

    Any other information as may be deemed by the superintendent to be necessary to evaluate the permit application.

    The superintendent will evaluate the data furnished by the user and may require additional information. After evaluation and acceptance of the data furnished, the superintendent may issue a wastewater discharge permit subject to terms and conditions provided herein.

    C.

    Permit conditions. Wastewater discharge permits shall be expressly subject to all provisions of this chapter and all other applicable regulations, user charges and fees established by the city. Permits may contain the following:

    1.

    The unit charge or schedule of user charges and fees for the wastewater to be discharged to the wastewater disposal system;

    2.

    Limits on the average and maximum wastewater constituents and characteristics;

    3.

    Limits on average and maximum rate and time of discharge or requirements for flow regulation and equalization;

    4.

    Requirements for installation and maintenance of inspection and sampling facilities;

    5.

    Requirements for installation, operation, and maintenance of pretreatment facilities;

    6.

    Specifications for monitoring programs which may include sampling locations, frequency and method of sampling, number, types and standards for tests and reporting schedule;

    7.

    Compliance schedules;

    8.

    Requirements for submission of technical reports or discharge reports;

    9.

    Requirements for maintaining and retaining plant records relating to wastewater discharge as specified by the superintendent, but in no case less than three years, and affording superintendent access thereto;

    10.

    Requirements for notification to and acceptance by the superintendent of any new introduction of wastewater constituents or of any substantial change in the volume or character of the wastewater constituents being introduced into the wastewater treatment system;

    11.

    Requirement for notification of slug or accidental discharges as provided in section 10.04.03.F., and reporting of permit violations;

    12.

    Requirements for disposal of sludges, floats, skimmings, etc.; and,

    13.

    Other conditions as deemed appropriate by the city to ensure compliance with this chapter.

    D.

    Permit duration. Permits shall be issued for a specified time period, not to exceed five years. The user shall apply to permit reissuance a minimum of one hundred eighty (180) days prior to the expiration of the user's existing permit. The terms and conditions of the permit may be subject to modification by the superintendent during the term of the permit as limitations or requirements as identified in sections 10.04.02 and 10.04.03 are modified or other just cause exists. The user shall be informed of any proposed changes in his permit at least thirty (30) days prior to the effective date of change. Any changes or new conditions in the permit shall include a reasonable time schedule for compliance.

    E.

    Permit modifications. Within nine months of the promulgation of a national categorical Pretreatment standard, the wastewater discharge permit of users subject to such standard shall be revised to require compliance with such standard within the time frame prescribed by such standard. Where a user, subject to a national categorical pretreatment standard, has not previously submitted an application for a wastewater discharge permit as required by section 10.04.07.B., the user shall apply for a wastewater discharge permit within one hundred eighty (180) days after the promulgation of the applicable national categorical pretreatment standard. In addition, the user with an existing wastewater discharge permit shall submit to the superintendent within one hundred eighty (180) days after the promulgation of an applicable national categorical pretreatment standard the information required by section 10.04.07.B.8. If the information previously submitted in an application is still current and adequate, only a letter from the user certifying such is required.

    F.

    Permit transfer. Wastewater discharge permits are issued to a specific user for a specific operation. A wastewater discharge permit shall not be reassigned or transferred or sold to a new owner, new user, different premises, or a new or changed operation without the approval of the superintendent. Any succeeding owner or user shall also comply with the terms and conditions of the existing permit.

( Ord. No. 94-27, § 4.02 )